Sugar Zone was acquired by Genesis Minerals in November 2026, susequent to a merger with Vault Minerals.
The Sugar Zone Project is an underground gold project located in Northern Ontario, Canada, approximately 30 km north of White River. The asset was previously owned and operated by several mining companies before being acquired by Silver Lake from Harte Gold Corp in February 2022.
Although mining operations commenced in 2019, in August 2023, Silver Lake elected to scale-back mining and processing activities and undertake an extensive drilling program aimed at improving geological understanding of the orebody and supporting the development of an updated mine plan. The drilling program comprised approximately 93,000 m and focused on the Sugar South Lode (‘Sugar South’), Middle Zone, and Sugar Main Lode (‘Sugar Main’).
The Sugar Zone processing facility incorporates a two-stage crushing and ball mill comminution circuit, together with a sulphide flotation circuit for the production of gold concentrate. The facility has an installed processing capacity of approximately 0.35 Mtpa and a permitted capacity of approximately 0.55 Mtpa.
Exploration activities continued during FY25, including a 101-hole diamond drilling program comprising approximately 18,219 m targeting the Sugar South area adjacent to Sugar Main. The drilling program contributed to the evaluation and delineation of Sugar South as an additional potential mining area within the project. The current mine restart plan includes the construction of a Southern Tailings Management Facility (‘STMF’), which is intended to provide tailings storage capacity over the life of the current Ore Reserve.
On 24 July 2026, Vault announced that it had received regulatory approvals to enable construction of the STMF with primary dam construction and pipeline installation scheduled for completion during the 2027 Canadian summer construction season. The Company continues to progress activities associated with the Sugar Zone Project, with underground development having recommenced in July 2026. This supports Vault’s target for a planned restart in the first quarter of FY28, with FY28 gold production guidance of 40-44 koz from Sugar Zone.