Through its acquisition of Dacian in 2023, Genesis acquired the Redcliffe Project, located approximately 45 km to 60 km north-east of Leonora.
The project covers approximately 330 km² of tenure located on the Mertondale Shear Zone, a regional geological structure containing several known gold deposits, including Redcliffe, Hub, GTS, Nambi, Kelly, Bindy and Mesa Westlode. Before Genesis acquired the project, Dacian completed drilling and technical studies to improve the geological confidence in the Hub, GTS and Nambi deposits and assess their development potential.
In February 2022, Dacian announced maiden Mineral Resource and Ore Reserve estimates for Hub and GTS, which were subsequently updated in July 2022. Dacian also completed grade-control, geotechnical, hydrological and sterilisation drilling for the proposed Hub and GTS open-pits. However, development of GTS was deferred because its higher forecast stripping ratio would require greater initial mining expenditure than Hub.
Following its acquisition of Dacian, Genesis prioritised the development of Hub as a comparatively highgrade, lower-capital source of open-pit ore for its Leonora and Laverton processing facilities. Hub was the only deposit within the broader Redcliffe Project that was mined during FY26. GTS and the other Redcliffe deposits remained development or exploration assets during the period.
In August 2024, Genesis completed the principal site establishment works required to commence mining at Hub. Open-pit mining commenced in September 2024, with the first ore placed on stockpile. Ore from Hub was first processed through the Leonora Mill in October 2024. Following the restart of the Laverton Mill in October 2024, Hub ore was also processed through that facility from December 2024.
During FY26, mining continued at Hub, including the commencement of the Stage 2 cutback of the central pit. Hub produced approximately 329 kt of ore at an average grade of 2.51 g/t gold, containing approximately 27 koz of gold. Ore mined at Hub was transported to both of Genesis’ operating processing facilities. Mining at the Hub South pit was completed during the first half of FY26.
As at 30 June 2026, mining was continuing in the remaining Hub open-pit areas and Genesis expected mining at Hub to be completed during the first half of FY27.